Your grid connection agreement, commercially assessed.

A flexible grid connection (FCA) gets your BESS connected sooner, but may limit feed-in, grid import and route to market. We assess which provisions may affect revenues and bankability, and offer input for your discussions with the grid operator.

PrioritiesExample, anonymised
  1. 2.1Termination at twelve months' noticeGrid access over the financing term uncertain
  2. 3.1Ramp rate of 6 % per minute at the grid connection pointMay restrict intraday trading and balancing
  3. 6.1Contractual penalties without a capRisk that is hard to quantify
01 Commercial impact

An FCA changes the business case of your BESS.

Technical provisions that may affect revenues and financing.

  • Bankability

    Terminable grid access

    Lenders may consider grid access as not secured.

  • Revenues

    Power bands

    Depending on the curve, midday feed-in may not be possible.

  • Route to market

    Ramp rate and schedule commitment

    At 6 % per minute, switching from full charge to full discharge takes around 33 minutes.

  • Balancing

    FCR release only after signing

    One revenue stream remains open at the financing decision.

  • Risk

    Penalties per quarter hour

    Without a cap, the risk is hard to quantify.

  • Capital expenditure

    Full construction cost contribution despite limits

    Some grid operators reduce it for flexible connections. A possible point for discussion.

Want the impact in euros? That is what our project optimization does, as a separate offer.

Go to project optimization
02 Topics

What we assess

We review the draft agreement and its annexes from a technical and commercial perspective and assign the provisions to eight topics.

  • 01Term and terminationNotice periods, duration of limits, grid expansion
  • 02Ramp rate and reactive powerMeasurement, exceptions, fallback
  • 03Power bands and scheduleCurve, reference plants, night window
  • 04Balancing and redispatchFCR, aFRR, mFRR, interventions
  • 05Contractual penaltiesReference value, event definition, cap
  • 06MiSpeL and metering arrangementOperating option, meter setup
  • 07Construction cost contribution (BKZ)Amount and reduction
  • 08Market comparisonRequirements of other grid operators and the BNetzA
03 Example

A possible approach for every point.

For each provision, we describe its possible effect on financing and operation and outline an approach as input for your discussions. The decision remains yours.

2.1 Termination at twelve months' notice

Priority

The grid operator may terminate at twelve months' notice. A new connection is then treated as a new application, possibly at a different grid connection point. For a debt-financed BESS, lenders may therefore consider grid access as not secured.

Possible approach

No ordinary termination by the grid operator during the financing term; extraordinary termination only with a cure period and step-in rights for lenders.

Reference: Section 11 (3) to (5)

04 Process

Three steps to an indicative assessment

  1. 1

    Send documents

    Grid connection agreement or FCA draft with all annexes and, where available, the grid connection commitment and metering arrangement.

  2. 2

    Working paper

    Non-binding technical and commercial assessment with possible approaches and open questions for the grid operator.

  3. 3

    Results call

    We discuss the results and which points you would like to clarify first.

The FCA analysis is a non-binding technical and commercial assessment. It is not legal, tax or financing advice and does not replace a legal review of the agreement.

Request an analysis

Included
  • Non-binding working paper (PDF)
  • Results call

We will get back to you personally and agree on the documents with you. Scope and liability are set out in the individual offer.

By submitting, you agree that we use your details to process your request. Details can be found in our privacy policy.

Arrange a preliminary call

In a short call, we clarify whether an FCA analysis makes sense for your project and which documents we need.

Book a preliminary call