Voltpark Logo
Back to Blog
Grid Connection

The First-Come-First-Served Principle for Grid Connections Is Ending. What BESS Developers Need to Know.

Voltpark Redaktion
March 11, 2026
The First-Come-First-Served Principle for Grid Connections Is Ending. What BESS Developers Need to Know.

From April 1, 2026, Germany's four transmission system operators are changing the procedure for large grid connection requests (>100 MW).

Instead of "first come, first served", it will now be "first ready, first served".

This primarily affects large-scale battery storage, data centers, and electrolyzers.

The competitive landscape is shifting significantly. Applications will now be collected in application rounds and prioritized based on project maturity.

What Counts for Maturity Assessment

  • Secured land (purchase or lease agreement)
  • Permitting status (BImSchG / building law)
  • Technical connection concept
  • Financing capability
  • Grid and system benefit (definition tbd)

💰 Costs: €50,000 application fee + €1,500/MW deposit upon acceptance.

What Does This Mean at DSO Level?

Some E.ON distribution system operators are already showing this trend. A SNAP assessment (Schnelle Netzanschlussprüfung) only serves as an initial orientation on grid conditions.

A serious review and possible reservation only occurs when concrete project progress is demonstrated — such as secured land and an ongoing building permit process.

The planned Grid Package 2026 is likely to embed this logic more broadly among DSOs.

Conclusion

Grid connection has always been the biggest value driver for BESS projects. With current developments, grid applications are becoming more expensive and existing grid connections / reservations even more valuable. For developers with capital access and advanced projects, this means tailwind. For everyone else, another hurdle on the path to grid connection.

Market a Project or Invest?

Voltpark connects developers and investors of renewable energy and battery storage projects in Germany.

Request Access

Related Articles

Negative Power Prices in Q1: From 14 Hours to 39 in Four Years

Negative power prices were long considered a summer phenomenon. With growing PV and wind capacity, even spring days now suffice to produce surpluses. 2026 is on a record pace — and the sunny half of the year hasn't even started.

Renewable Surplus Has Increased Fifteenfold: Why Short-Term Flexibility Is the New Bottleneck in the Power System

Between 2022 and 2025, renewable energy surplus in the German grid has increased fifteenfold. Residual load analysis reveals: The central bottleneck is shifting from installed capacity to temporal flexibility — precisely the sweet spot for battery storage.

At What Development Stage Should I Sell My BESS Project or Pipeline?

The common rule of thumb is: sell at Ready-to-Build. But rising development costs and scarce grid connection commitments are changing the equation. The optimal time to sell is a strategic portfolio decision.