Voltpark Logo
Back to Blog
Grid Connection

The First-Come-First-Served Principle for Grid Connections Is Ending. What BESS Developers Need to Know.

Voltpark Redaktion
March 11, 2026
The First-Come-First-Served Principle for Grid Connections Is Ending. What BESS Developers Need to Know.

From April 1, 2026, Germany's four transmission system operators are changing the procedure for large grid connection requests (>100 MW).

Instead of "first come, first served", it will now be "first ready, first served".

This primarily affects large-scale battery storage, data centers, and electrolyzers.

The competitive landscape is shifting significantly. Applications will now be collected in application rounds and prioritized based on project maturity.

What Counts for Maturity Assessment

  • Secured land (purchase or lease agreement)
  • Permitting status (BImSchG / building law)
  • Technical connection concept
  • Financing capability
  • Grid and system benefit (definition tbd)

💰 Costs: €50,000 application fee + €1,500/MW deposit upon acceptance.

What Does This Mean at DSO Level?

Some E.ON distribution system operators are already showing this trend. A SNAP assessment (Schnelle Netzanschlussprüfung) only serves as an initial orientation on grid conditions.

A serious review and possible reservation only occurs when concrete project progress is demonstrated — such as secured land and an ongoing building permit process.

The planned Grid Package 2026 is likely to embed this logic more broadly among DSOs.

Conclusion

Grid connection has always been the biggest value driver for BESS projects. With current developments, grid applications are becoming more expensive and existing grid connections / reservations even more valuable. For developers with capital access and advanced projects, this means tailwind. For everyone else, another hurdle on the path to grid connection.

Market a Project or Invest?

Voltpark connects developers and investors of renewable energy and battery storage projects in Germany.

Request Access

Related Articles

Is Now a Good Time to Buy PV Project Rights?
Market Analysis
May 22, 2026

Is Now a Good Time to Buy PV Project Rights?

Two years ago, build-ready PV project rights cost north of EUR 100/kWp – today we see prices down to EUR 20/kWp. Cannibalization is pushing the solar market value to around 1.3 ct/kWh. But with a green-power storage system, the PV revenue nearly doubles. Is this the contrarian entry point?

Two Auctions Until the System Change: Ground-Mounted PV at 4.94 ct/kWh

The March 2026 ground-mounted PV auction was again clearly oversubscribed, with a bid-to-award ratio of around 2.0 – the volume-weighted award value was 4.94 ct/kWh. Despite tougher competition, prices are rising. Why, and what the last two auctions before the 2027 system change mean for build-ready projects.

Germany: 866 DSOs for 52 Million Grid Customers – What the Fragmentation Means for Developers

866 distribution system operators serve Germany's 52 million grid customers – Spain manages with 333, the Netherlands with 6. This fragmentation turns every grid connection into a standalone project, makes flexible connection agreements vary widely, and even shapes the transaction market. Why the grid area matters as early as site selection.